European energy company Vattenfall is building the Nordlicht wind cluster, which will have a net capacity of more than 1.6 GW ...
Vattenfall and BASF have taken a significant step in advancing the Nordlicht offshore wind projects by awarding contracts to ...
The wind farms will have a combined capacity of more than 1.6GW. Construction is set to begin in 2026, with commissioning in 2028. The Nordlicht 1 project will have a capacity of 980MW, while ...
Vestas said the company has secured a firm order for 68 of its model V236-15.0 MW wind turbines for Vattenfall’s Nordlicht 1 offshore wind project. The agreement announced March 31 is for the ...
Construction of the 980MW Nordlicht 1 and the 630MW Nordlicht 2 projects is slated to begin next year and the wind farms are expected to be operational in 2028. Nordlicht 1 alone, at the time of ...
For Nordlicht I, the contract covers the transportation and installation support of 68 Vestas V236-15.0 MW wind turbines, with work scheduled to begin in the summer of 2027.
Swedish power utility Vattenfall said on Tuesday it has made a final investment decision for two wind farm projects in the German North Sea, Nordlicht 1 and 2, the first of which is expected to ...
BASF Sells Share in Nordlicht Wind Farms Back to Vattenfall. Published: March 25, 2025 at 12:23 p.m. ET. Share. Resize. About Dow Jones Newswires.
Vattenfall and BASF have taken a significant step in advancing the Nordlicht offshore wind projects by awarding contracts to four suppliers for essential components and installation services. The ...